FOUNDRY : MOULDING LINE ACE

First pouring; Wednesday January 7th 2015



Disassembly of the old moulding line were conducted during holidays in 2014 by the staff of the foundry.

Installing the new ACE moulding line

Despite a very tight schedule of 4 months for commissioning, it was observed:

3 months mounting, 1 month of testing and adjustment to the production of the first mould.

The first pouring was made on 01.07.2015. The following week, we have produced between 150 and 200 moulds daily.

The development continues in parallel with production to reach full capacity in the 2nd half of 2015.